I want to run parallel executions of different test sequences with TestStand 2.0

I read the question and answer from the 01/22/2002 from LC_garza, but is it also possible to run different sequences at the same time on TestStand 2.0
Thanks for your help
0 Kudos
Message 1 of 3
(3,162 Views)
Hi,

I pulled my example from previous response and loaded into TS 2.0. I ignored the warning about being a 2.01 sequence file and continued loading it.

I setup the station options to use the modified parallelprocessdiff.seq. Then loaded the example sequence0.seq and selected the Single Pass execution.

It ran as expected ( ie 4 parallel executions). Although the launching of sequence0.seq seems a bit hit or miss ( reason unknown - the path and name is correct) (see other comment about this - using 1 -4 instead of 0 - 3 works more reliable).

Regards
Ray Farmer
Regards
Ray Farmer
0 Kudos
Message 2 of 3
(3,162 Views)
Hi
it only runs if I load the second sequence and start this one in Single Pass.
0 Kudos
Message 3 of 3