11-03-2014 04:35 AM
hi,
In testsand 2012 is an example Auto Schedule.
my question is in this example sequence, there are subsequences parallel sequential etc.
during execution the status bar shows BatchModel.seq
the Model defined for the file is a Sequential Model in File Properties.
could be bcos it uses ModelOptions Callback &
Parameters.ModelOptions.NumTestSockets = 4
11-03-2014 04:46 AM
The setting you are looking for is in the SequenceCall steps. They are all configured for "New Execution".
Please review the advanced settings for each call.
Norbert
11-03-2014 04:59 AM
ya thanks Norbert