Hello,

 

I'm really new to Teststand so please excuse me.

 

I am building a sequential test with LabView based steps.

I need also to have a process (vi) running all of the time to monitor the health of the DUT, if it goes outside parameters, then the power should be removed & test aborted.

 

I have invetisgated "Run Async VI" and also read on the forums about using a sub-sequence.

In my experiement with Async VI i was not able to see how to pass variables into the VI (Module tab is missing) or take pass/fail output.

And i not not fully understand how to make a sub-sequenece.

 

Could someone please tell me which is the best solution, and walk me through the implementation?

 

Thanks.

Labview 2010, TestStand 2010
0 Kudos
Message 1 of 2
(2,742 Views)

Hi

 

the following should help get you started:

 

List of Examples

 

sequence in parallel

 

code module in parallel

 

 

Regards
Ray Farmer