unexpect line performance

I have two problems here:

1. When I use make a  2D curve, it looks like the connect the last point of my data the the first point, the slash form time 1s to time 0s isn't my expect.(Please see the figure attached)

 

2.When I want to  use  2 Y Axis, I can't change the begin\end of Y axis to make the two Y Axis align well, I want to know what I need to do?

0 Kudos
Message 1 of 3
(3,517 Views)
 Sorry, the first problem is my fault. only need some one answear the second question.
0 Kudos
Message 2 of 3
(3,508 Views)

Hi ws.horton,

 

The first Y axis on DIAdem plots must stretch from 0% to 100% vertically.  All subsequent Y axes can be configured at will to cover, say, 0% to 45% or 55% to 100%.  Please try creating 2 additional Y axes and assigning the first of your curves to axis 2 and the second of your curves to axis 3.

 

Let us know if you still have trouble with this,

Brad Turpin
DIAdem Product Support Engineer