KW 42-43, 14.10.13 - 25.10.13
This Document is a short summary of development activities during Sprint 9 of myRIO Balancing Robot development.
It is part of the agile development model used for the development of myRIO Balancing Robot as described here: https://decibel.ni.com/content/docs/DOC-30572 and https://decibel.ni.com/content/docs/DOC-32062
Adrian Schmid, 100%, 30 Story Points
Team TU-Darmstadt, 25 Story Points
Team DHBW, 25 Story Points
Lukas Kurmann, 10 Story Points
90 Story Points
U-037: Prototype Redesign (ADP, TU-Darmstadt), 100 Story Points
U-038: Courseware, 40 Story Points
U-040: VT Inital Training, 20 Story Points
U-043: myBOT Final SW, 100 Story Points
Total: 260 Story Points
U-037: Prototype Redesign (ADP, TU-Darmstadt):
The TU-Darmstadt ADP Team decided to not work within the Agile Model. They want to perform their work in an standard process model.
In order to still being able to plan the progress of the development process, their workload will be divided into the remaining sprints.
This sprints progress will be defined as 50 Story Points.
U-043: myBOT Final SW:
U-043 too big for one user story. Changed to Epic E-043. Introduction of:
U-044, U-045, U-046, U-047, U-048, U-049
Introduction of U-050 and U-051
U-037: Prototype Redesign (ADP, TU-Darmstadt), 50 Story Points
U-044: FPGA Architecture, 20 Story Points
U-045: Mathematical Model, 20 Story Points
Burndown Chart at the Beginning of the Sprint.
Product Backlog increases again. Introduction of U-043.
Burndown Chart at the End of Sprint 9
Product Backlog increases again. See Impediment 2 and Impediment 3.