Hello,
I have a Array of Clusters and a lot of SubVIs using this Cluster. If I change the Cluster ( f.e. thorugh adding a new INT-value to it), I need to go in all of my SubVIs and also do the same changes there. There must be an easier way to do this, but I was not able to find it out. I tried thorugh refernece, but it didnt work 😞 I was also not able to find a solution here in this forum.
Can somebody help pls?
Solved! Go to Solution.
12-05-2011
05:47 AM
- last edited on
06-09-2025
04:05 PM
by
Content Cleaner
Serdj,
I am not sure if this is your problem, but have you tried type defining the cluster?
regards,
aCe
12-05-2011 05:55 AM
Thanks aCe, it looks like the solution I was looking for. I will try it out these days. Thanks a lot!!!