I need a way to set up different ramp and soak profiles using a recipe. Each
recipe will not have the same number of cycles. Can someone give me some
hints as I am very new to Lookout.
0 Kudos
Message 1 of 2
(3,642 Views)
You can use the integral object to calculate the ramp and soak by giving ramp
rate as input.
Using the sequencer object (Lookout 4.0 only) you can sequence different ramp
and soak cycles. and predefine inputs to these objects using recipies.

Vinod Mathews

norm dingle wrote:

> I need a way to set up different ramp and soak profiles using a recipe. Each
> recipe will not have the same number of cycles. Can someone give me some
> hints as I am very new to Lookout.